When there’s a powerline shown on the proposal, is it provided to show that it can’t be built on?
Not exactly. The powerline is shown so we can see where it is in relation to the proposed building. It is not a ban on building on your block, but a building cannot go on the line or too close to it.
Powerline mains generally need a minimum of 2.0 to 2.7m clearance from any proposed building. This may increase if the lines are not insulated. Service lines need a minimum of 1.2 to 1.5m. These clearances are there for the safety of occupants, trades and services that may need to work nearby.
If the building is clear of those distances, the line can usually stay where it is. If the building gets in the way, the line is either moved underground or pivoted to another point of connection. This is called a change in service.
Once your project is in the planning approvals process, we apply to Evoenergy on your behalf. Evoenergy generally provides a change of service sketch showing an underground service to your house. The work is then quoted, and if it was not already part of your project, we issue a project variation for you to sign. Evoenergy decides the date of the change, which can take several weeks and can affect your project schedule.
CGFB-Q-0371 · last reviewed 24 November 2026
Related questions
- How are new connections made to a new building from an existing building? These connections include sewer, electricity, gas, water, storm water
- If a residence has two separate utility meters, can a Secondary Residence have a third meter?
- At what stage during the build will the power, water, gas and sewer facilities be functional?