What is the process if we need to get our power lines that connects energy to our house moved because of the proposed development?
This process is called a change in service. Once you have entered the planning approvals process, we will apply to EvoEnergy on your behalf for their approval. They will provide a sketch of where the new service will go. EvoEnergy generally always provides a change of service sketch as underground powerlines to your house. If you do not want an underground service, this is something we would have to request in our application.
Once the service sketch/service mark has been approved/issued, we will provide this to our electrical partner. They will provide a quote for the works, which includes the EvoEnergy fees/works and also the electrician's works as part of the process. If this has not already been included as part of your project, a project variation will be issued for you to sign.
Once the scope of works is confirmed/approved with you, the electrician will then make a submission with EvoEnergy to book in a date for a change of service. This can take several weeks and it is ultimately EvoEnergy who decides when the change of service date will be. The date they provide can have a bearing on the project schedule, as most works can't proceed while the overhead powerlines are still overhead.
CGFB-Q-0289 · last reviewed 21 November 2026
Related questions
- How are new connections made to a new building from an existing building? These connections include sewer, electricity, gas, water, storm water
- If a residence has two separate utility meters, can a Secondary Residence have a third meter?
- At what stage during the build will the power, water, gas and sewer facilities be functional?
- When there’s a powerline shown on the proposal, is it provided to show that it can’t be built on?