Questions & Answers › Before we start on site
At what stage during the build will the power, water, gas and sewer facilities be functional?
Short answer: all the services that are part of your project must be finished and certified by practical completion. The exact point during the build when each one is switched on varies from project to project.
What the law says
Under the Building Act 2004 (A2004-11), it is unlawful to occupy or use a building, or part of a building, until a Certificate of Occupancy and Use has been issued. To apply for it, the certifier must first issue a Certificate of Completion. The application also needs the installation and compliance certificates for the work, including the electrical, gasfitting and plumbing work.
The Territory Plan 2023 (NI2023-540), Residential Zones Policy, requirement 10, says no new gas network connections are allowed to new or existing developments, including redevelopments. Gas work on your project therefore means work such as relocating an existing gas line or meter. It does not mean a new gas connection.
Under the Planning (Residential Zones) Technical Specifications 2026 (NI2026-303), spec 29.1, the utility providers (electricity, water, gas, sewerage and stormwater) must endorse that the development can be serviced.
--------------------
How we do it
Under our HIA contract, practical completion means the building work is complete apart from minor omissions. It also means we have done everything the contract requires of us so that a Certificate of Occupancy and Use can be obtained. Working, certified services are part of that.
After the walkthrough:
In the week or so after the walkthrough, we gather the installation and compliance certificates. The licensed tradespeople who did the electrical, plumbing, drainage and any gas work prepare them.
Your private building certifier checks the documents and issues a Certificate of Completion.
Your certifier then lodges the application for the Certificate of Occupancy and Use with Building Registration. This takes about three weeks, depending on government processing.
Do not move in or rent the building out until the certificate has been issued.
When each service is switched on during the build: services are installed in steps as the build goes on, and some steps depend on the utilities rather than on us. Icon Water decides on water and sewer connections, and Evoenergy decides on any change to the power supply. If you need to know the timing, for example because work affects services to your existing home, ask your construction team. They can tell you what applies to your project.
CGFB-Q-0141 · last reviewed 24 November 2026
Related questions
- How are new connections made to a new building from an existing building? These connections include sewer, electricity, gas, water, storm water
- If a residence has two separate utility meters, can a Secondary Residence have a third meter?
- What is the process if we need to get our power lines that connects energy to our house moved because of the proposed development?
- When there’s a powerline shown on the proposal, is it provided to show that it can’t be built on?