If a residence has two separate utility meters, can a Secondary Residence have a third meter?
Short answer: yes, in most cases a Secondary Residence can have its own meter. How it works is different for water, gas and electricity, and the utility providers have the final say.
What the law says
The Planning (Residential Zones) Technical Specifications 2026 (NI2026-303), specification 29.1, require that a development can be sufficiently serviced. The relevant utility providers (electricity, water, gas, sewerage and stormwater) must endorse that the utility connections comply with their standards. The specifications do not set how many meters a block can have.
A Secondary Residence cannot be given its own title, either by subdivision or by unit titling (Territory Plan 2023, NI2023-540, Part F01 Subdivision Policy, assessment requirement 5). It stays on the same title as the main home. So the rules for subdivided leases or unit-titled dual occupancies do not apply to it.
Gas: the Residential Zones Policy (NI2023-540, Part E01, assessment requirement 10) says no new gas network connections are allowed to new or existing developments. Ask us to check this for your block before you plan on a gas meter for the Secondary Residence.
_____
What the utility providers require, and how we handle it
These are utility provider rules, not planning rules.
Water (Icon Water). A secondary water meter is possible on most single-title blocks, but it is rarely done because the benefit is small. Icon Water provides the water and sewer account, and only excess water can be charged to a tenant. If the block were subdivided into separate leases, each dwelling would need its own Icon Water connection and meter. That does not apply to a Secondary Residence.
Gas (EvoEnergy). A secondary gas meter can usually be provided on a single-title property, managed by EvoEnergy. See the gas point above, which we will check for your block.
Electricity (EvoEnergy). Typically only one service is provided to a block, but this can be changed in some cases. EvoEnergy decides where the service connects. A second meter may need a Service Mark, which is EvoEnergy's permission to change the equipment on site. EvoEnergy identifies this in the approvals process.
Costs and options at CGFB
For electricity, there are two options. A second meter board gives a separate account and bill, and our price guide for an average project is $2,500 to $5,000. A sub meter costs around $700. It does not give a separate bill, but it lets you work out how much power the new building has used. A water sub meter is also around $700. A secondary water meter costs $2,500 to $10,000.
CGFB is happy to help with enquiries about adding meters to your project. We apply to the utility providers on your behalf during the approvals process.
CGFB-Q-0124 · last reviewed 24 November 2026
Related questions
- How are new connections made to a new building from an existing building? These connections include sewer, electricity, gas, water, storm water
- At what stage during the build will the power, water, gas and sewer facilities be functional?
- What is the process if we need to get our power lines that connects energy to our house moved because of the proposed development?
- When there’s a powerline shown on the proposal, is it provided to show that it can’t be built on?