Questions & Answers › Before we start on site
How are new connections made to a new building from an existing building? These connections include sewer, electricity, gas, water, storm water
In short, each service is extended from what already serves your block. That means your existing house's switchboard, sewer drain, water supply, gas line and stormwater system. A licensed tradesperson usually runs a new line in an underground trench to the new building. Where the extension isn't possible or allowed, the service is moved, upgraded or given its own connection to the network. The work must be done by licensed trades, meet Australian Standards, and in some cases be approved by Evoenergy (electricity) or Icon Water (water and sewer) before it goes ahead.
How it is worked out for your block
The services are planned during design, not on the day. Our services and access plans show where each service runs. Your Site Scope Report and Site Scope Proposal set out the site-specific work and its price, including service connections.
We also refer the design to the utility companies early. Icon Water now assesses submissions to decide whether a fee applies under its Water and Sewerage Capital Contributions Code. That is why you may be asked to complete a minor works form.
Sewer
The new building's drains are joined to the existing sewer drain or to the property's sewer tie, which is the connection point to Icon Water's network. The work must meet the Plumbing Code of Australia (National Construction Code Volume Three) and AS/NZS 3500.2 (sanitary plumbing and drainage).
For an attached extension, drainage pipes can run under the new structure if they are laid in UPVC. For a detached building, sewer lines cannot run under it, so existing lines may need to be diverted. Our plumber advises on this.
If the sewer tie needs to move, Icon Water must agree first. Icon Water owns the sewerage easement and decides what it will allow near its assets.
Water
A new water line is usually branched from the existing supply after the meter and run to the new building. The work must meet AS/NZS 3500.1 (water services).
The rules change if the property is to be unit titled or subdivided:
- Unit titled: under the Utilities (Technical Regulation) (Water and Sewerage Code) Approval 2024, in effect from 1 July 2024, separate unit meters under a single service tie are mandatory. Separate service ties are allowed but not required.
- Subdivided into separate leases: each lease must have its own independent connections to the Icon Water network.
If your project needs a rainwater tank, the tank is also connected to the plumbing it serves. Its overflow goes to the stormwater system.
Stormwater
Roof water from the new building is collected by gutters and downpipes. It then runs in underground pipes to the existing stormwater system or the block's stormwater connection point. Where a tank is required, it first goes to the tank. The design must meet AS/NZS 3500.3 (stormwater drainage).
Some work affecting public stormwater assets or easements needs approval from Transport Canberra and City Services (TCCS) or Icon Water.
Electricity
Power is usually run from the existing main switchboard in an underground cable (a sub-main) to a new switchboard in the new building. The electrical work must meet AS/NZS 3000 (the Wiring Rules). That standard sets the cable protection and burial depth, among other things.
Sometimes the existing supply to the property is not big enough for the added load and the meter or service needs upgrading. That needs Evoenergy's endorsement. Because the cost can't be known until Evoenergy responds, a power meter upgrade is one of the few items that may appear as a provisional sum.
If the new building sits where the overhead power line to your house runs, the line has to be changed. This is called a change of service. Once your project is in the planning approvals stage, we apply to Evoenergy on your behalf. Evoenergy provides a sketch showing where the new service will go. You also need at least 1.5 m clearance from Evoenergy poles and pillars.
Gas
The ACT is moving away from gas. The Climate Change and Greenhouse Gas Reduction (Natural Gas Transition) Amendment Act 2023 stops most new connections to the gas network.
Whether gas can be extended to a new building on your block has to be checked for your specific project. Your design and Site Scope Report will show whether it is proposed. Most new buildings now use electric appliances and heat pump hot water. Where a detached addition triggers a whole-house energy assessment, a heat pump is required.
Where gas pipework is installed or altered, it must meet AS/NZS 5601.1 (gas installations). If the new building's footprint clashes with an existing gas line or gas meter, the line or meter has to be relocated. This is most common for projects in the front of the block.
Easements
You cannot build on top of an underground sewer, stormwater or electrical easement. Building within 2 m of one requires reinforced concrete piers to protect the pipe or cable and your new building.
Sign-off
In the ACT, plumbing, drainage, gasfitting and electrical work must be done by tradespeople licensed under the Construction Occupations (Licensing) Act 2004. When the work is finished, the trades provide compliance certificates. Your certifier needs these to issue the Certificate of Completion before the Certificate of Occupancy and Use can be applied for.
Our "Connection of Existing Building to New Building" item covers services disconnection and relocation where it applies.
CGFB-Q-0076 · last reviewed 24 November 2026
Related questions
- If a residence has two separate utility meters, can a Secondary Residence have a third meter?
- At what stage during the build will the power, water, gas and sewer facilities be functional?
- What is the process if we need to get our power lines that connects energy to our house moved because of the proposed development?
- When there’s a powerline shown on the proposal, is it provided to show that it can’t be built on?