When does the progress payment for the “Project completion” get triggered? Will there be a case where I must make this payment and I am unable to make use of the property to rent, i.e., Certificate of Occupancy and use is not yet obtained
The Project Completion invoice (the final 10% of the project value) is due when practical completion is reached. It is not due when you move in, and it does not wait for the Certificate of Occupancy and Use (COU). So yes, you may have to pay it before you are allowed to rent the property.
What the law says
It is against the law to occupy or use a new building until a COU has been issued. That includes renting it out. The ACT Government issues the COU. Only the building certifier you appointed can lodge the application. Before that, the certifier must issue a Certificate of Completion.
How we do it
Under our contract, practical completion means that the building works have reached the stage where we certify they have been completed in accordance with the contract, except for minor omissions. Where applicable, it also means we have done all that we are required to do under the contract to enable a certificate of occupancy to be obtained.
We record practical completion at the Customer Project Walkthrough. We walk through the project with you and hand it over, and we ask you to sign the walkthrough document so that we agree it together. The contract also lets us declare practical completion under clause 23.1, and that does not depend on your signature.
Minor defects are listed at the walkthrough. They do not stop practical completion being reached. In some cases the walkthrough notes allow the final invoice to be adjusted, for example by a deduction until a condition is met. Defects are then fixed through the warranty log.
The COU comes after the walkthrough. In the week or so after it, we gather the installation and compliance certificates your certifier needs. The application can ideally be lodged about a week after the walkthrough. The COU then takes about three weeks on average, subject to government processes. Allow roughly a month after practical completion before you can move in or rent the property.
If paying at that point is not feasible, for example because your bank will not release funds until the COU is issued, please talk to us. Our contract is with you, not your bank. We are happy to discuss delaying the payment, but we keep the discretion to charge interest on a late payment.