The stages will not be completed until they are paid for upfront?
No. We complete each construction stage first and then invoice you. We do not ask for the stage payments upfront.
The only payments made before building starts are the Deposit (5%) and the Planning Approvals payment (5%). Together these make up 10% of the project value and cover the development and building approval costs. These are the only payments required until we start building.
After that, each progress payment is tied to a stage of the build: Floor System Complete (20%), Wall and Roof Frames (15%), Close Up Complete (15%), Fixings Complete (15%), Painting Complete (15%) and Project Completion (10%). When a stage is finished, we send you a progress payment report with photos and details, and then issue the invoice. Payment is generally due within five working days after the stage is completed.
Clause 12 of your HIA agreement has the full terms for progress payments and interest on late payments.
CGFB-Q-0388 · last reviewed 24 November 2026
Related questions
- Financing residential building projects - what are the options if we want to borrow money to build?
- Can you explain what Prime Costs are in plain english?
- Is the deposit made when they give the green light to build?
- When does the progress payment for the “Project completion” get triggered? Will there be a case where I must make this payment and I am unable to make use of the property to rent, i.e., Certificate of Occupancy and use is not yet obtained