What does it mean to achieve practical completion and when is the final invoice due?
Practical completion means that the building works have reached the stage where the builder certifies that they have been completed in accordance with the contract, except for minor omissions. Where it applies, it also means the builder has done all that the contract requires to enable a certificate of occupancy to be obtained.
We record practical completion at the Customer Project Walkthrough, which is signed by us and by you. The contract also gives us the power to declare that practical completion has been achieved (clause 23.1), and that does not depend on you signing the form. Minor defects listed at the walkthrough do not stop practical completion from being reached.
The final invoice is the Project Completion payment, which is 10% of the project value. It is due when practical completion has been reached. It is not due when the Certificate of Occupancy is issued. Progress payments are generally due within five working days after the stage is completed.
The Certificate of Occupancy comes after the walkthrough. The ACT Government issues it. Only the certifier you appointed can lodge the application, ideally about a week after the walkthrough. The government process then takes about three weeks on average. This means you may have to pay the final invoice before the certificate is issued.
Please add any defects to the warranty log so we can rectify them. If paying on time is a real difficulty, for example because your bank will not release the final loan amount until the certificate is issued, please talk to us. We are happy to discuss delaying payment, but we keep the discretion to charge interest.