We have a variation that is a negative amount (a credit). Why can't we just have that credited to our next progress payment?
While a negative variation (credit) does reduce the overall contract value, it doesn’t automatically reduce the next scheduled progress payment. Each progress payment corresponds to a fixed stage value in the contract and becomes due once that stage is substantially complete.
Progress payments are fixed, binary amounts tied to specific construction milestones – they cannot be altered mid-project. For this reason, any credits from negative variations are applied to the final contract balance, not to individual progress payments. This ensures consistency, transparency, and alignment with the HIA contract structure.
When a negative variation is approved, we issue a variation invoice that clearly shows the credit amount in your favour (e.g. -$1,298 for the removal of a water tank). This credit is then reflected in your final invoice.
To keep things transparent, we do not apply interest to variation amounts – whether positive or negative. Interest charges and late payment calculations only apply to progress payments, as defined in your contract.