Prime cost items, what are they and do they have a margin associated?
Prime Cost Items are the allowances in your Project Proposal for items you choose yourself, such as tapware, toilets, basins, tiles, appliances and flooring. The HIA contract calls them Prime Cost Items. We simply call them allowances.
We do not apply a builder's margin to them. This is outlined in your Project Proposal. If you spend more than the allowance, we add no margin to the extra cost.
If you choose items within the allowance, there is no additional cost. If you choose items above or below the allowance, the price is adjusted by the difference. You can choose any product you like, and you are not limited to our suppliers.
The builder's margin does apply to variations, such as adding a new deck that is not in your proposal. We give you the cost and you sign it off before that work starts.