I believe the progress payment stage has not been fully completed - why do I have to pay the invoice?
What the contract says
Our contracts follow the industry-standard HIA progress payment schedule. Each progress payment is a fixed amount tied to a defined stage of construction. A stage counts as complete when it reaches “substantial completion” under the contract. It does not need every small item finished. A stage can be complete even if minor touch-ups or finishing items remain, as long as the primary components of that stage are finished.
Progress payments are due once we issue the invoice. Payment is generally due within five working days after the stage is completed. The only grounds for not paying are a significant fault that stops the stage working for its purpose, or a major omission in that stage. Problems with other parts of the project do not change when a stage payment is due.
If a payment is late, the HIA contract (Schedule 1) sets interest at 14%, calculated daily. Clause 12 of the contract has the full terms for progress payments and interest.
How we handle it
Sometimes we are still waiting on a supplier or a key trade to return and complete a minor item. In these cases we will typically move on to the next stage so your project is not delayed, while we re-schedule the trade or wait for the supply to arrive.
We issue a progress payment report with photos and details each time a stage is completed. If you believe a stage is not substantially complete, or that an invoice is wrong, raise it with your project manager. You can also email accounts@cgfb.com.au with the invoice number, details of your concern and any supporting documents. We will review it and respond within 3-5 business days.