Why do I need a Building Approval (BA) if I already have a Development Approval (DA)?
A Development Approval (DA) and a Building Approval (BA) are two separate approvals. They check different things, so having a DA does not mean you can start building.
What the law says
A DA is the planning approval under the Planning Act 2023 (A2023-18). It checks whether the development is allowed on your block and meets the planning rules. These include setbacks, building height, plot ratio, Crown lease requirements, tree protection, parking and access, and impacts on neighbours. The Territory Planning Authority assesses the DA.
A BA is the construction approval under the Building Act 2004 (A2004-11). It checks whether the building work can actually be built to the National Construction Code and the building regulations. This covers structure, energy efficiency, fire safety, waterproofing, drainage and accessibility. A licensed building certifier assesses it.
A DA does not fully assess whether the building can be constructed. A project can have a DA and still need changes before it can get a BA.
How we do it
In most residential projects the DA comes first and the BA follows. The BA is generally issued by a private certifier, and you can nominate your own.
A change needed for the BA, such as a structural, drainage, fire separation or energy change, can mean updating plans already approved at DA. That is why we consider both approvals early in the design.