Questions & Answers › Approvals and planning rules
Who lodges the application and to whom?
What the law requires
Under the Building Act 2004 (A2004-11), it is against the law to occupy or use a building, or part of a building, without the required Certificate of Occupancy and Use (COU).
The application for a COU is lodged with Building Registration. It can only be lodged by the certifier appointed for your project, so you do not lodge it yourself. The certifier is appointed by you as the land owner, not by the builder.
Before the application is lodged, the certifier must issue a Certificate of Completion. This states that the building work is complete and satisfactory, with all the relevant documents provided. Those documents include the installation and compliance certificates for the electrical, gasfitting and plumbing work.
How we do it
We usually engage Capital Certifiers. You are free to nominate a private certifier of your choice instead. Please tell us early if you want to use your own.
After the project walkthrough, we gather the installation and compliance certificates the certifier needs. Ideally the application can be submitted to the certifier about a week after the walkthrough. Your certifier then issues the Certificate of Completion and lodges the COU application.
The COU is issued by the ACT Government. On average this takes about three weeks, subject to government processes. Please do not move in or rent the property until it has been issued.