When is Demolition application required?
What the law says (planning, DA)
Under the Planning (Exempt Development) Regulation 2023 (SL2023-21), some demolition does not need a Development Application (DA).
Houses. Demolishing a single dwelling, or part of one, is exempt from DA (sch 1, s 1.132). This does not cover a dwelling that has a party wall (s 1.132(4)). Before a house is demolished, you must take reasonable steps to give your adjoining occupiers written information about it: site and elevation plans, and any other information the Territory Planning Authority requires (s 1.18). The exception is urgent demolition to deal with a risk of death or injury, serious harm to the environment or significant damage to property.
Sheds, garages, carports and other Class 10 structures. On a block in a residential zone, demolishing a Class 10 building or structure is exempt from DA (s 1.133(1)(a)).
Conditions that still apply. The general exemption criteria in sch 1, part 1.2 must be met. For example, the work must not breach the Heritage Act 2004 or the Urban Forest Act 2023. It must not be on a registered heritage place unless the Heritage Council gives the advice described in s 1.13. Affected residential premises are also restricted (s 1.16). If any condition is not met, or the house has a party wall, the demolition is not covered by these exemptions and you should check with ACT Planning whether a DA is needed. An exemption from DA does not remove other laws, such as the Building Act 2004 (s 1.6).
Building Approval (BA) and how we do it
BA is a separate approval from DA. It is assessed by a licensed building certifier under the Building Act 2004 (A2004-11).
Demolishing a house will generally need BA before demolition starts. Demolishing a Class 10 structure may be exempt from BA. ACT Planning's guidance is that demolition is BA-exempt where the building would be BA-exempt if it were built today and the other general rules are met.
If BA is needed, it must be issued before demolition starts. The builder then gets a commencement notice from the building certifier, and demolition can start once that notice has been issued.
Tell us what you want to demolish and we will check whether a DA, a BA, or both apply. You can also check at: https://www.planning.act.gov.au/applications-and-assessments/development-applications/check-if-you-need-a-da and https://www.planning.act.gov.au/applications-and-assessments/building-approvals/check-if-you-need-a-ba