When does completion time start counting?
Completion time is the period we have to finish your project, from when construction begins to practical completion. The count starts 15 days after we receive building approval (the stamped plans) from the private certifier.
Completion time is counted in working days, not calendar days. It can be extended if a delay happens. When that happens we send you a time delay letter showing the date it was sent, the number of working days delayed and the reason.
The full terms are in your signed HIA agreement.