Questions & Answers › Approvals and planning rules
When does an extension project trigger a DA and not just a BA?
What the law says
An extension needs only a Building Approval (BA), and no Development Approval (DA), if it is exempt development under the Planning (Exempt Development) Regulation 2023 (SL2023-21), made under the Planning Act 2023 (A2023-18).
For an extension to a single dwelling, the main pathway is Schedule 1, section 1.130 (Compliant single dwellings). The extension is exempt if all of these apply:
- the dwelling will be the only dwelling on the block;
- the work, as built, complies with the Single Dwelling Housing Development Control declared under section 14(1)(a) of the Regulation, and with any relevant District Controls;
- the neighbour information required by section 1.18 has been given to adjoining occupiers; and
- the general exemption criteria in section 1.10 are met. These include compliance with the lease (s 1.14), no increase to 2 or more dwellings on the block (s 1.15), and compliance with the mandatory matters development control (s 1.17A).
An extension needs a DA when it cannot meet these requirements. A DA is also needed in these cases:
- the project needs a lease variation;
- the project is a duplex, which needs a DA even if it complies;
- the addition is detached and works as a separate dwelling. It must then be approved as a Secondary Residence, and a Secondary Residence always needs a DA.
Where a project is compliant except for a minor breach, part 1.3A of the Regulation (sections 1.19 to 1.19D) allows an application for an exemption declaration (the "1N"). The Territory Planning Authority must decide it within 10 working days. It may make the declaration only if the non-compliance is minor and the breach will not do any of the following:
- adversely affect someone other than the applicant;
- more than minimally increase the environmental impact; or
- more than minimally increase shadowing to a habitable room or principal private open space of another block between 9am and 3pm on the winter solstice.
It may need support from the affected neighbour. A declaration expires 3 years after it is made. It only tests the development controls. It is not an assessment against the Zone Policy outcomes.
Exempt from DA does not mean no approval. A DA or an exemption only checks planning. Building Approval is a separate check under the Building Act 2004 (A2004-11) that the building can be built to the National Construction Code.
How we handle it
We check your extension against the Single Dwelling Housing Development Control and the District Controls before we design it too far.
- If the extension does not intrude on the boundary setbacks or the solar and building envelopes and meets the mandatory criteria, it can go straight to a building certifier.
- If there is one minor breach, we seek the exemption declaration first and then get building approval from a certifier.
- If the breach is not minor, or there is more than one, we lodge a DA.
A Secondary Residence always needs a DA. So does any project that needs a lease variation.
CGFB-Q-0673 · last reviewed 24 November 2026