When do I have to pay my progress payments?
What the contract says
Under your HIA building contract, progress payments are due as set out in the invoice we issue. The invoice is our written claim for that stage. Each progress payment is a fixed amount tied to a defined stage of construction. Your contract sets out the stages and the percentage for each one.
A stage counts as complete when it reaches 'substantial completion' under the contract. It does not need every small item finished. A stage can be complete even if minor touch-ups or finishing items remain, as long as the primary components of that stage are finished. A minor or non-critical item is not a reason to hold back payment. Issues outside the listed stages do not change the payment schedule.
If a payment is late, clause 12.3 and Schedule 1 item 11 of the contract allow us to charge interest at 14% per annum on the unpaid amount. It can be charged if a payment is still unpaid 5 days after the invoice is issued. Interest applies only to progress payments, not to variations. Clause 12 also allows us to suspend the building works after written notice if a progress payment is not made. If you pay within 5 business days of that notice, we resume works within a reasonable time.
How we handle it
We complete each stage first and then invoice you. We send a progress payment report with photos and details each time a stage is completed. Payment is generally due within five working days after the stage is completed.
If you believe a stage is not substantially complete, or that an invoice is wrong, raise it with your project manager. You can also email accounts@cgfb.com.au with the invoice number, details of your concern and any supporting documents. We will review it and respond within 3-5 business days.
CGFB-Q-0695 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?