What is the timeframe in which a Completeness Check is required to be completed for a Development Approval Application by the Planning Department?
The DA Gateway team generally aims to undertake completeness checks within 10 working days. This could fluctuate depending on how many submitted DA’s are currently being examined, and staffing. The team utilises the Minimum Documentation Requirements Checklist (which can be found here: https://www.planning.act.gov.au/__data/assets/pdf_file/0009/1096911/minimum-documentation-requirements-for-lodgement-of-a-development-application.pdf) to complete this process. If this timeframe is exceeded, it is recommended that the DA Gateway Team is contacted for follow up.