Questions & Answers › Approvals and planning rules
What is the difference between building approval and development approval?
A Development Approval (DA) and a Building Approval (BA) are two different approvals. They check different things.
What the law says
Development Approval (DA) is the planning approval. It is assessed under the Planning Act 2023 (A2023-18) against the Territory Plan 2023 (NI2023-540). It checks whether the development is allowed on your block and whether it meets the planning rules. These include setbacks, building height, plot ratio, Crown lease requirements, tree protection, parking and access, and impacts on neighbours. The Territory Planning Authority assesses the DA.
Building Approval (BA) is the construction approval. It is assessed under the Building Act 2004 (A2004-11). It checks whether the building work can actually be built to the National Construction Code and the building rules. This covers structure, energy efficiency, fire safety, waterproofing, drainage and accessibility. A licensed building surveyor, your nominated certifier, assesses the BA.
A DA does not guarantee a BA. A project can have a DA and still need changes before it can get a BA.
Which approvals does my project need? Not every project needs both, and the two kinds of exemption are separate. Whether work is exempt from DA is set by the Planning (Exempt Development) Regulation 2023 (SL2023-21). Whether it is exempt from BA depends on the building exemption rules, not the planning exemption rules.
- Some work is exempt from BA. For example, demolition is BA-exempt where the building would be exempt if it were built today and the other general exemption rules are met.
- Some work is exempt from DA. An extension, for example, will typically need only a BA. It needs a DA as well if it cannot meet every exemption rule, including the general exemption criteria in the Regulation (sch 1, s 1.10).
- A Secondary Residence always needs a DA. Under the Regulation, exempt development must not increase the number of dwellings on a block to two or more (sch 1, s 1.15), and a Secondary Residence is a second dwelling on the block.
- If your project needs a Crown lease variation, a DA is required whatever the project type. A dual occupancy typically needs a DA for this reason as well as for the building itself.
How this works in practice
In most residential projects the DA comes first and the BA follows.
To check whether your work needs a BA, see: https://www.planning.act.gov.au/applications-and-assessments/building-approvals/check-if-you-need-a-ba
CGFB-Q-0757 · last reviewed 24 November 2026