What is the Building Line (Planning and Development Act)?
What the Territory Plan says
These definitions are in the Territory Plan 2023 (NI2023-540), Part G Dictionary.
The building line is a line drawn parallel to a front boundary, along the front face of a building or through the point on the building closest to that boundary.
For setting the building line, a terrace, landing, porch, balcony, deck or verandah counts as part of the building if it is more than 1.5m above finished ground level or is covered by a roof. A fence, courtyard wall or retaining wall does not count as part of the building.
The building line is not set by the setback. It follows where the building actually sits. It can be closer to the front boundary than the minimum front setback, for example where a departure from the setback has been approved. It can also be further back.
Effect on the front zone
The front zone is the area between the front boundary and the building line, or the minimum front setback, whichever is greater. It is never more than 10m from the front boundary.
- If the building line is closer to the front boundary than the minimum front setback, the front zone reaches out to the setback.
- If the building line is further back than the minimum front setback, the front zone reaches out to the building line.
Effect on the primary building zone
The primary building zone is the area between the front zone and a line 12m further back from the front zone.
- If the building line is closer than the setback, the primary building zone starts at the setback line and runs 12m back.
- If the building line is further back than the setback, it starts at the building line and runs 12m back.
The minimum front setbacks are in specification 14.3 and Tables 1 to 4 of the Planning (Residential Zones) Technical Specifications 2026 (NI2026-303).
CGFB-Q-0599 · last reviewed 24 November 2026