What is involved in the Development Approval (DA) process?
A Development Approval (DA) is the planning approval. The ACT planning authority checks whether your project meets ACT planning rules and can go ahead on your block. A DA is not a Building Approval (BA). The BA is a separate step, covered at the end.
What the law says
The DA is assessed under the Planning Act 2023 (A2023-18). The project is measured against the Assessment Outcomes and Assessment Requirements in the Territory Plan 2023 (NI2023-540). Assessment Requirements, such as site coverage, are mandatory. For a residential zone, the Planning (Residential Zones) Technical Specifications 2026 (NI2026-303) can be used as a benchmark for showing the Assessment Outcomes are met. They are a possible solution, not a mandatory checklist.
Whether you need a DA depends on the project:
- A Secondary Residence always needs a DA.
- An extension does not need a DA if it meets every rule in the Single Dwelling Housing Development Control and the relevant District Controls. It then only needs a BA.
- If your project needs a Crown lease variation, it needs a DA, whatever the project type.
Depending on the project, the DA looks at matters such as:
- Setbacks and building envelopes
- Building height and site coverage
- Crown lease requirements
- Tree protection
- Neighbour impacts and overlooking
- Solar access and overshadowing
- Parking and vehicle access
- Easements and utility constraints
- Landscaping and planting area
- Waste and stormwater
- Subdivision and unit titling requirements, where they apply
The usual steps are:
- Prepare the application. The plans and supporting documents are finalised and lodged. The documents you need depend on the project and are set out in the Planning (Minimum Development Application Documentation) Guideline 2026 (No 1) (NI2026-13). For most residential DAs this includes a site plan, floor plans, elevations, sections, a roof plan, and shadow diagrams where solar access needs to be shown. A dual occupancy also needs a Design Response, which is separate from the Development Outcomes Report. The guideline's checklist is not comprehensive, so the planning authority can ask for more.
- Completeness check. The planning authority checks the application has what it needs before accepting it for assessment.
- Public notification. Every DA is publicly notified, through a notice on the planning website, a sign on your block and letters to adjoining neighbours.
- Referrals. The application may go to bodies such as Icon Water, Evoenergy and Transport Canberra and City Services for advice.
- Assessment and decision. Under the Planning Act 2023 the legal timeframe for the assessment stage is 30 working days if no neighbour makes a representation. It is an extra 15 working days if a representation is received. If the planning authority formally asks for more information, the clock pauses until you supply it.
The legal timeframe is only the assessment stage. For a Secondary Residence or dual occupancy, the whole planning approvals stage generally takes 8 to 10 months.
Getting a DA does not mean you can start building. You still need a Building Approval (BA) before construction begins. The BA is a separate technical check against the National Construction Code, usually run by a private certifier. A project can have a DA and still need changes before it gets a BA.