What is involved in the Building Approval (BA) process?
Building Approval (BA) is the approval that checks your project can be built safely and meets the building rules, including the National Construction Code (NCC). It is a different approval from Development Approval (DA), which looks at planning matters such as setbacks, height and the effect on neighbours.
What the law says
BA is assessed under the Building Act 2004 (A2004-11). It is generally issued by a private building certifier licensed in the ACT. The certifier reviews the documents prepared by the project team against the NCC, Australian Standards, structural requirements and safety requirements. The certifier does not usually design the project.
Depending on the project, the BA assessment can cover:
- Structural engineering
- Energy efficiency (EER)
- Drainage and stormwater
- Waterproofing
- Fire safety
- Accessibility and livable housing requirements
- Site classification and footing design
- Existing structures
- Service authority requirements
In most residential projects the DA comes first and the BA follows. A DA does not guarantee a BA. A Secondary Residence always needs both. Some building work does not need a BA at all. Whether it does depends on the building exemption rules, not the planning exemption rules, so each project needs to be checked.
Documents for a BA can include architectural plans, structural engineering plans, energy reports and stamped plans, a site classification report, drainage plans, specifications, consultant reports and proof of Development Approval where one is required.
_______________
How we do it
We manage the BA process for you. In practice it runs like this:
- A licensed building surveyor is appointed as your certifier. You can nominate your own certifier. Please tell us early if you want to.
- Building approval is applied for and the required fees are paid. Your 10% project deposit and planning payment covers the required development and building approval costs.
- A licensed builder is appointed and the building commencement notice is obtained.
- Construction starts once the commencement notice has been issued.
Our design team, engineers, energy assessors and other consultants prepare the documents with you and we take them to the certifier. Working through the BA requirements early helps identify technical and construction issues before building begins. That reduces the risk of redesign, delays and extra cost, which is why we want the documentation settled before a fixed price building contract is signed.