What is development approval, and will my project require it?
Development approval is mandatory for secondary residences and can take anywhere between 40-60 working days.
The development approval process involves:
- Development Application Submission
- This will be done by us once you have signed off on your project plans and other requisite paperwork.
-
Completeness Check
-
After submission, an officer will check the completeness of our submission to verify if it is fit for assessment.
-
Completeness check can take up to 10 working days.
-
-
Development Application Lodgement
-
The DA is only lodged once it passes completeness check and the required fees are paid.
-
-
Public Notification and Assessment
-
Public notification occurs concurrently with assessment and has a legal timeframe of 30 working days if no representation is received.
-
The legal timeframe is extended by 15 working days if representation is received.
-
-
Notice of Decision
-
A notice of decision will be sent to notify us of whether the DA is approved with stamped plans, approved with conditions, or rejected.
-
More information can be found in Planning Act 2023.