What is an exempt development and the BA process?
What the law says
Exempt development is development that does not need a Development Approval (DA). The rules are in the Planning (Exempt Development) Regulation 2023 (SL2023-21), made under the Planning Act 2023 (A2023-18). For an extension to a single dwelling, the main pathway is schedule 1, s 1.130. The extension is exempt if all of these apply:
- the dwelling will be the only dwelling on the block (s 1.130(1)(a), s 1.15);
- the work complies with every rule in the Single Dwelling Housing Development Control (the version in force today is NI2025-492) and the relevant District Controls;
- before work starts, you give your adjoining neighbours the site and elevation plans, and shadow diagrams if any part goes past the solar building envelope (s 1.18); and
- the general exemption criteria in s 1.10 are met. These include keeping clear of easements and utility access spaces, heritage and tree laws, the terms of your lease, and the mandatory matters control.
You still need a DA if the extension cannot fully comply, if the project needs a lease variation, or if the block has or would have two or more dwellings. A detached addition that works as a separate home must be approved as a Secondary Residence, and a Secondary Residence always needs a DA.
If a project is compliant except for one minor breach of a setback, the building or solar envelope, or the minimum private open space rule, you can apply to the Territory Planning Authority for an exemption declaration instead of a DA (s 1.19B and s 1.19C). BA is still needed after that.
Exempt from DA does not mean no approval at all. Building Approval (BA) is a separate approval under the Building Act 2004 (A2004-11). A DA or an exemption only checks the planning rules. BA checks that the work can be built to the National Construction Code. Small Class 10a buildings such as certain garages, sheds and carports are typically exempt from BA if they meet the size requirements. Whether work is exempt from BA depends on the building exemption rules, not the planning exemption rules, so each project needs to be checked.
How we do it
We check which approvals your project needs before we design it too far. Where a DA is needed, it comes first and the BA follows. A DA does not guarantee a BA, so we consider both early in the design. A private building certifier assesses the BA. We manage the process for you:
1. A licensed building surveyor is appointed as your certifier. You can nominate your own certifier. Please tell us early if you want to.
2. Building approval is applied for and the required fees are paid. Your 10% project deposit and planning payment covers the required development and building approval costs.
3. A licensed builder is appointed and the building commencement notice is obtained.
4. Construction starts once the commencement notice has been issued.
Depending on the project, the BA documents can include architectural plans, structural engineering plans, energy reports, a site classification report and drainage plans. We prepare these with you and take them to the certifier.
CGFB-Q-0398 · last reviewed 24 November 2026