Questions & Answers › Getting started with us
What if we want to change the plans?
Yes, you can change your plans. What it costs, and what is possible, depends on when you ask. The earlier you tell us, the simpler and cheaper it is.
While we are still designing
Design changes are unlimited and are included in your design fee. After each design meeting you get updated plans with a clear version number, which you can download from your customer portal. Look through them, note anything you would like changed, and your Customer Designer will discuss and record your requests and include them in the next version.
We review the estimated costs with you as the design develops. If a change pushes the estimate above your budget, we explain the trade-offs so you can decide what suits you.
After you sign the HIA agreement and proposal
You can still make changes, and we have a change control process to manage them. What is possible depends on how far your approvals have progressed.
Smaller changes. Minor changes that do not affect your building or development approvals, such as exterior finishes, materials or inclusions, can generally be made through the inclusions process. Different selections may still change the price of materials or installation. Swapping one item for another against a Prime Cost allowance has no builder's margin. You pay the difference if it costs more, and you get a credit if it costs less.
Changes that need a redesign. Adding rooms, or anything that affects your approvals, usually needs a redesign. Our design team's work is charged at $180 an hour including GST. We give you an estimate of the hours and cost for your approval before we start. We then revise the plans and reprice the affected work, because this changes your fixed-price building agreement. A redesign can delay your project by two to four weeks, and any extra approval time is separate.
The revised scope, final price and any change to the timeframe are recorded as a variation. You approve it before the changed building work goes ahead. Work that is not in your proposal at all, such as a new deck, is a project variation and our builder's margin applies to it.
After Development Approval and Building Approval are granted
We cannot change the overall layout or floor plan. Smaller changes, such as exterior finishes, materials or inclusions, can usually still be made. If you are thinking about a change, tell us as early as you can and we will advise whether it can be done and what it would cost.
What the law says
A Development Approval is a planning approval under the Planning Act 2023 (A2023-18). It assesses matters such as the size of the building, setbacks, height and site coverage. If a change affects something the approval assessed, the approval may need to be amended, or a new application made, and the planning authority decides. Some small projects are exempt from Development Approval if they meet the relevant requirements, but the position, size or layout you choose can affect that exemption.
A Building Approval is assessed by a certifier against the National Construction Code and the Building Act 2004 (A2004-11). A change that affects construction compliance may need the certifier to approve amended plans.
How we handle it
Either kind of approval change can add time. We will tell you which applies to your change before you decide.