Questions & Answers › Your agreement and your rights
What if there are minor warranty issues? E.g. scratches, chips in veneer etc.
What the law says
The Building Act 2004 gives a statutory warranty for residential building work that needs a building approval and costs $12,000 or more (s 87, s 88). The builder warrants that the work has been or will be carried out in accordance with the Building Act, in a proper and skilful way, and with good and proper materials (s 88 (2)).
The warranty is taken to be part of the contract even if it is not written in. A contract term that tries to limit it is void (s 91 (3)).
The warranty runs for six years after the completion day for structural elements, including components of external walls (with weatherproofing). It runs for two years for non-structural elements. The completion day is the day the work is completed or the day the contract ends, whichever is later (s 85 (1)).
How we do it
Under our HIA agreement, practical completion means the building works have reached the stage where we certify they have been completed in accordance with the contract, except for minor omissions. It also means we have done all that is required to enable a certificate of occupancy to be obtained.
Small items like scratches or chips in veneer are minor. They do not stop practical completion being reached, and they do not stop the Project Completion invoice becoming due.
Minor items are recorded at the Customer Project Walkthrough. Some notes in the walkthrough document can adjust the final invoice, for example a deduction until a condition is met. The document still states that practical completion has been achieved.
Under clause 23 of the HIA agreement, you have 65 working days after completion to notify us of defects. Please enter every item in the warranty log so nothing is missed. We will do our best to fix defects within the agreed scope of the project as soon as we can.
The 65 working days is a reporting window for smaller items. It is not the length of your warranty.
If you are unsure about a specific item, raise it with your project manager.
CGFB-Q-0689 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?