What happens if my preferred design cannot meet planning or building approval requirements?
What we do
We work with you to revise the plans so they meet the planning and building requirements, while keeping your main objectives wherever possible. During the design process, design changes are unlimited and included in your design fee. We keep refining the plans with you until you are satisfied. At each design meeting we also review the estimated building and siteworks costs, so you can see how any change affects your budget.
Planning and building approvals overlap. Development Approval (DA) comes first and Building Approval (BA) comes second. A change needed for BA, such as a structural, drainage or fire separation change, can mean updating plans already approved at DA. We consider both together early in the design so this is less likely.
Signing the Design Agreement does not commit you to construction. You review the plans and the fixed-price proposal before deciding whether to build with us.
If you need changes after you sign the building agreement, a redesign is charged at $180 an hour including GST. We give you an estimate of the hours and cost for your approval before we start. A redesign can delay your project by two to four weeks, with any extra approval time separate. Once DA and BA have been granted, we cannot change the overall layout or floor plan. Smaller changes, such as exterior finishes, materials or inclusions, can usually still be made.
What the law says
Planning (DA). The main test for a development application is the assessment outcomes in the Territory Plan 2023 (NI2023-540). The Planning (Residential Zones) Technical Specifications 2026 (NI2026-303) may be used as a benchmark. A design that meets a relevant specification and comprehensively addresses the assessment outcome needs no further assessment on that point. If a design does not meet a specification, the DA is not automatically refused. You can propose a different design and show how it still achieves the assessment outcome. An Assessment Requirement in the Territory Plan, such as site coverage, is mandatory and must be met. The final approval decision rests with the relevant authority, not with us.
Building (BA). BA is assessed by your nominated certifier in line with the National Construction Code 2022 and the Building Act 2004 (A2004-11).
If your project is approved with conditions (Planning Act 2023, A2023-18). A condition cannot be ignored. It continues to apply until it is formally changed. Your options are to revise the plans to meet the conditions, which may need to be endorsed by the Territory Planning Authority. You can also apply to amend the approval, or ask the Territory Planning Authority to reconsider its decision, generally within 20 working days. Where the decision is reviewable, you can apply to the ACT Civil and Administrative Tribunal (ACAT) for review.
CGFB-Q-0880 · last reviewed 24 November 2026
Related questions
- When fire resistant walls are needed, such as when building within 1.8 metres of an external wall on the block, where is this marked on the plans? Does this also incur additional costs for the customer?
- Can we change from a modification design to a custom design during the design process?
- Can you terminate the design process?
- Why are the follow-up design meetings held online or at your office?