Questions & Answers › Your agreement and your rights
What does practical completion mean?
What our contract says
In our HIA building agreement, practical completion means that the building works have reached the stage where we, the builder, certify that they have been completed in accordance with the contract, except for minor omissions. Where applicable, it also means we have done all that we are required to do under the contract to enable a certificate of occupancy to be obtained.
Practical completion is formally reached when we and you sign the Customer Project Walkthrough. The contract also gives us the power to declare that practical completion has been achieved (clause 23.1). That power does not depend on you signing the form.
Minor defects listed at the walkthrough do not stop practical completion being reached. You can add them to the warranty log so we can fix them. The Project Completion invoice (the final 10% of the contract) is due when practical completion is reached. It is not due when the Certificate of Occupancy is issued.
What the law says
Practical completion is not the same as a Certificate of Occupancy. Under the Building Act 2004 (A2004-11), section 69, the construction occupations registrar issues the certificate. Under section 76, it is an offence to occupy or use a building, or allow someone else to, before a certificate of occupancy has been issued for it. You cannot move in or rent the building out until you have the certificate.
How we do it
The certificate comes after the walkthrough. Your appointed certifier lodges the application, and only your certifier can lodge it. The government process takes about three weeks on average, subject to government processes.
CGFB-Q-0687 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?