Questions & Answers › Approvals and planning rules
What changes to a plan would trigger a need for a resubmission of a DA?
What the law says
The Planning (Exempt Development) Regulation 2023 (SL2023-21), made under the Planning Act 2023 (A2023-18), says when a change to an approved plan needs no new approval. Under s 7(2), a change to development covered by an existing Development Approval is exempt from needing development approval if it is one of these:
- a permitted construction tolerance;
- a change that would not need development approval if it were made after the development was finished; or
- the addition of something that is itself exempt development.
In plain terms: if the change would be exempt from a DA once the building is finished, it generally does not trigger an amendment or a resubmission. The change must still meet the general exemption criteria in schedule 1, part 1.2 of the Regulation. These include the lease, easement, heritage and tree criteria.
Small construction variations
Schedule 2 of the Regulation allows small differences between the approved plans and what is built. For a point that must be sited on, or within 900mm of, a boundary, the tolerance is 50mm. For a point sited more than 900mm from a boundary, it is 340mm. Height can vary by up to 340mm. A tolerance does not apply if the change moves the building outside the solar building envelope without approval. Nor does it apply if the change increases ponding or diverts surface water onto other land, or changes the number of storeys (sch 2, ss 2.2 and 2.3).
Changes that are not covered
Under s 7(3), the exemption does not apply if the change results in non-compliance with any of these:
- schedule 1, s 1.15, which stops development increasing the number of dwellings on a block to 2 or more;
- schedule 1, s 1.41, the rule for class 10 buildings and other structures within 1.5m of a side or rear boundary; or
- the requirement in schedule 1, s 1.130 that there be no more than 1 dwelling on a block.
A change outside these rules may need the Development Approval to be amended. You generally apply to amend the existing approval rather than lodge a completely new DA. There is no general rule such as 'a 5% or 10% change is allowed'. It depends on what is being changed and how it affects the approved development. ACT Planning can approve an amendment, approve it with conditions, or refuse it.
A change that a condition of the approval requires is already part of the approval. The Notice of Decision may still require the amended plans to be submitted to the Territory Planning Authority for endorsement before the approval takes effect or work starts.
Separate approvals can also apply. Under the Building Act 2004 (A2004-11), ss 31-32, amended building plans after Building Approval go to the certifier. The certifier can approve them only where the statutory requirements are met, including that the building would not be significantly different from the building in the original approved plans.
How we do it
Before any change is built, we check it against the approved plans and the DA conditions. We work out whether it stays covered by the existing approval or whether a DA amendment is needed. We also check whether a Building Approval amendment is needed. For example, if a driveway crossing over the public verge is moved, City Services approval is needed even where no DA amendment is.
If an amendment is needed, we prepare and lodge it for you. ACT Planning decides it, and we cannot promise the outcome.
CGFB-Q-0494 · last reviewed 24 November 2026