What are the new Condensation Management requirements for Roofs?
Condensation management is a requirement of the National Construction Code (NCC) 2022. In the ACT the NCC applies through the Building Act 2004 (A2004-11), and your building certifier checks it at building approval.
The Performance Requirement and Verification Method are in Volume Two of the NCC, Section H, Part H4. The Deemed-To-Satisfy provisions are in Part 10.8 of the ABCB Housing Provisions. Following the Deemed-To-Satisfy provisions is one accepted way to comply. The detail below comes from those provisions.
Roofs are susceptible to condensation because water vapour is lighter than air and tends to rise. A roof therefore needs an escape path for water vapour, in the form of a space or cavity. The roof space needs to be 20mm in height. It must be located immediately above one of the following:
- the primary insulation layer (the insulation batts); or
- sarking above the primary insulation layer, where the sarking is at least as permeable as a class 4 vapour control membrane that complies with AS4200.1 (in climate zone 7, which includes the ACT); or
- the ceiling insulation.
Roof spaces also need to be ventilated through evenly distributed openings. The opening details depend on the roof pitch and the type of roof, as shown in Table 10.8.3 of the Housing Provisions. An example of where such openings can go is in the eave.
CGFB-Q-0666 · last reviewed 24 November 2026
Related questions
- When fire resistant walls are needed, such as when building within 1.8 metres of an external wall on the block, where is this marked on the plans? Does this also incur additional costs for the customer?
- Can we change from a modification design to a custom design during the design process?
- Can you terminate the design process?
- Why are the follow-up design meetings held online or at your office?