What are the key changes for Pliable Building Membranes (water barriers)?
Pliable building membranes (sarking) that are installed on the outside of the primary insulation layer now need to be vapour permeable, meaning they let water vapour pass through. The primary insulation layer is the most interior insulation layer of a wall or roof, for example the insulation batts in an external stud wall.
In climate zone 7 (the ACT) the membrane needs to be highly permeable. It must be at least as permeable as a class 4 vapour permeable membrane that complies with AS4200.1. The same applies in climate zones 6 and 8.
Membranes also need to comply with AS4200.1 (Pliable building membranes and layers) and be installed in accordance with AS4200.2.
Where a pliable building membrane is not installed in an external wall, the external cladding is kept separate from water sensitive materials by a drained cavity. This does not apply to single skin masonry, where the brick is both the structural and the external layer.
CGFB-Q-0658 · last reviewed 24 November 2026
Related questions
- When fire resistant walls are needed, such as when building within 1.8 metres of an external wall on the block, where is this marked on the plans? Does this also incur additional costs for the customer?
- Can we change from a modification design to a custom design during the design process?
- Can you terminate the design process?
- Why are the follow-up design meetings held online or at your office?