What the law says
The rules are in the Planning (Exempt Development) Regulation 2023 (SL2023-21), schedule 1, section 1.48 (Fences and freestanding walls generally). You do not need development approval for a fence or freestanding wall on a block if all of these are true:
- It is not too high. A mesh fence in an industrial zone can be up to 2.7m above datum ground level. In any other case, a fence panel or wall can be up to 2.3m above datum ground level, and a support post or column can be up to 2.5m above datum ground level.
- No part of it is between a front boundary and the building line. The building line runs parallel to the front boundary along the part of the building closest to it.
- No part of it diverts or concentrates the flow of surface water in a way that causes ponding or sends water onto other land.
- It meets the general exemption criteria in section 1.10 of the regulation. These cover easements and access clearances, plumbing and drainage clearances, heritage, trees and environment, the lease, no multiple occupancy dwellings, affected residential premises, and the mandatory matters.
A few things to know:
- A gate that forms part of a fence or wall is treated as part of the fence or wall.
- Section 1.41 still applies. The boundary clearance area is the strip 1.5m inside a side or rear boundary. All Class 10 buildings and structures in that strip together can have a cross-section area of no more than 30m2. A boundary fence does not count towards that limit, but a freestanding wall does.
- A fence on an open space boundary (between leased and unleased land) is dealt with separately in section 1.49.
- A fence or wall forward of the building line is not exempt under section 1.48. Our answer on front fences explains the courtyard wall and other front fence rules in the Residential Zones Technical Specifications 2026 (NI2026-303), specifications 18.1 and 18.2.
- Being exempt from development approval does not remove other legal requirements. Other Territory laws still apply (section 1.6), and the work may still need building approval under the Building Act 2004.