Questions & Answers › Approvals and planning rules
What are the different kinds of easements and how do they impact the design?
An easement is an area of land that another person or organisation has the right to use or access. Most easements are for utilities: stormwater, sewer, water and electricity. Right of way easements are different. They are not for utilities. They let owners of blocks without direct road access cross other land to reach the road, and they are rare in the ACT. An easement does not automatically stop you building, but it can limit where a building, driveway or retaining wall can go. You can check what is on your block using ACTmapi's utility infrastructure map.
What the law says
The Planning (Residential Zones) Technical Specifications 2026 (NI2026-303), specification 29.1, require that a development can be serviced. The relevant utility providers (electricity, water, gas, sewerage and stormwater) must endorse it. That endorsement confirms that earthworks, utility connections, buildings, pavements and landscape features comply with utility standards, access provisions and asset clearance zones.
The specifications do not create easements. They also do not set an access width or height for them. Those figures come from the utility owners, who decide their own requirements.
How we handle it in design
We first work out which easements are on your block and who owns each one. Each owner has its own access requirement. The figures below are what the owners currently ask for.
Electricity easement (Evoenergy). You need a clear, unobstructed machinery access, 1.5m wide and at least 2.4m high, to any pole location on your block. We show this access on the site plan.
Stormwater easement (TCCS). A new dwelling or building is not permitted within a stormwater easement. In new suburbs, access is along the easement itself. In other locations, access of 2.5m x 2.5m is required.
Sewer easement (Icon Water). Icon Water owns the sewerage easement and decides what it will allow near its pipes. The access needed depends on how deep the pipe is:
Pipe less than 2.2m deep: a path 1.8m wide with 2.65m height clearance.
Pipe 2.2m to 3.0m deep: a path 2.5m wide with 2.85m height clearance.
Pipe deeper than 3.0m: assessed individually by Icon Water.
Most developments need between 1.8m and 2.5m.
You cannot build within the pipe protection envelope, which is the protected space around the pipe. It is not the same as the whole easement. Concrete piers do not load the no-load zone, so building can be possible there. Our current guidance is that building closer than 2m from an easement will need reinforced concrete piers to protect the easement and your project. Retaining walls can sometimes be built in or near an easement if they keep the required clearances and stay outside the envelope. Icon Water must approve any work near or over its easement in writing, and this is separate from Development Approval.
We have sometimes gained approval with less access than these figures. That is the entity's decision in each case and is not guaranteed. Do not design to less than the figures above unless the entity has agreed in writing.
Because of all this, an easement may mean we reposition or redesign the building, and we may need written approval from the utility owner.
CGFB-Q-0375 · last reviewed 24 November 2026