What are the causes in a powerline being moved?
A powerline needs to be moved when your proposed structure interferes with it. This means the structure is built on the line's existing location or too close to it. Powerline mains generally need a minimum of 2.0 to 2.7m clearance from any proposed building. This may increase if the lines are not insulated. Service lines need a minimum of 1.2 to 1.5m. The main reason for these clearances is the safety of occupants, trades and services that may need to work nearby.
When this happens, the line is either moved underground or pivoted to another point of connection. This is called a change in service. Evo Energy generally provides a change of service sketch showing an underground service to your house. If you do not want an underground service, we need to request that in our application.
Once you have entered the planning approvals process, we apply to Evo Energy on your behalf for their approval. When the sketch is approved, we pass it to our electrical partner, who quotes for the works. The quote includes Evo Energy's fees and works and the electrician's works. If this was not already part of your project, we issue a project variation for you to sign. The electrician then books the change of service date with Evo Energy.
This can take several weeks, and Evo Energy decides the date. The date can affect your project schedule, because most works cannot proceed while the overhead powerlines are still overhead.
CGFB-Q-0376 · last reviewed 24 November 2026
Related questions
- When fire resistant walls are needed, such as when building within 1.8 metres of an external wall on the block, where is this marked on the plans? Does this also incur additional costs for the customer?
- Can we change from a modification design to a custom design during the design process?
- Can you terminate the design process?
- Why are the follow-up design meetings held online or at your office?