The project has not been finished as there are still defects in the build. Why am I receiving a project completion invoice?
What the law says
The Building Act 2004 (A2004-11) does not decide when a final invoice is due. That comes from your building contract. The Act does protect you after you pay. Section 88 builds a statutory warranty into every contract to carry out residential building work that it covers. The builder warrants that the work has been or will be carried out in accordance with the Building Act, in a proper and skilful way and in accordance with the approved plans, and that good and proper materials are used. Under section 91 (3), a term of a contract that tries to limit or modify the operation of Part 6 is void.
The warranty applies to residential building work that needs a building approval and costs $12,000 or more. It runs for six years after the completion day for structural elements, and two years after the completion day for non-structural elements. Paying the final invoice does not end it.
How the contract works
The Project Completion invoice is due when practical completion is reached. It is not due when every defect has been fixed, and it is not due when the Certificate of Occupancy is issued.
Under the contract, practical completion ‘means that the building works have reached the stage where the builder certifies that they have been completed in accordance with the contract, except for minor omissions and, where applicable, has done all that the builder is required to do under the contract to enable a certificate of occupancy to be obtained’.
Clause 23.1 of the contract gives us power to declare that practical completion has been achieved. That power does not depend on you signing the form.
How we do it
We record practical completion at the Customer Project Walkthrough. We ask you to sign the Customer Project Walkthrough document so that we agree it together. Any minor defects are listed there. They do not stop practical completion from being reached.
Sometimes the walkthrough document has notes that allow the final invoice to be modified, for example a deduction until a condition is met. The document still states that practical completion has been achieved.
Please put every concern into the warranty log so nothing is missed. We will do our best to fix defects within the agreed scope of the project as soon as we can. Some defects may fall outside our scope, and we will tell you if that is the case.
If you believe the work is not at practical completion, or the invoice is wrong, please raise it with your project manager. You can also email accounts@cgfb.com.au with the invoice number, your concern and any supporting documents. For other questions about the contract, email contracts@cgfb.com.au. If paying on time is difficult, please talk to us. We are happy to discuss delaying payment, but we keep the discretion to charge interest.
CGFB-Q-0798 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?