Questions & Answers › Your agreement and your rights
Rock is preventing work commencement, who pays to get it removed? Will this affect the time for completion?
The owner pays for rock. Our contract does not cover excavating rock, or any other material that cannot be readily excavated by a backhoe. If rock like this is found on your block, the cost of removing it is payable by the owner.
Our Fixed Price Guarantee does include site work such as excavation for underground services, footings and foundations. Rock and similar hard material is the exception. Rock is a ground condition, not something left behind by old structures, so it can be found on any block. The risk is lower on projects that do not involve major excavation.
Rock can also affect the time for completion. Our time commitment is subject to conditions, including unforeseen circumstances and delays outside our normal control. Only working days are counted when a delay happens. If a delay is recorded, we send you a time delay letter. The letter states the date it was sent, the number of working days delayed and the reason. Those days are then added to the time for completion.
Please email contracts@cgfb.com.au if you want to talk through how this applies to your project.
CGFB-Q-0683 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?