Q - What are the steps associated with delays from the Department?
If the Department is not convinced that a setback encroachment satisfies the criteria, it can raise this at different points in the application. Each point adds delay. How much depends on when the Department raises it.
What the law says
Under the Planning Act 2023 (A2023-18), the legal timeframe for assessing a development application is 30 working days if no neighbour makes a representation. It is extended by 15 working days (45 in total) if a representation is received.
The Department can ask for further information or for an amendment during assessment. A request for further information must allow 20 working days or more for the applicant to respond. The applicant can apply for a further 20 working days. The time taken to respond does not count towards the legal assessment period. If a notified application is amended or more information is provided, public notification may be required again.
If the application is rejected, the applicant can ask the Territory Planning Authority to reconsider, generally within 20 working days. The applicant can also apply to the ACT Civil and Administrative Tribunal (ACAT) for review, where the decision is reviewable.
What we do (our practice)
The Department may take these steps, usually in this order:
- A request for further information (s 141). There is no fee. We need to give evidence of development in similar proximity to the fence in the surrounding area.
- A request to amend the development application (s 144). There is no fee. We need to give changed plans.
- Advice that the Department will reject the application unless we make an s 144 application. The fee is $330.95. If the change is required, notification fees may also apply: $1,298.50 for a major change or $321.50 for a minor change.
- If the application is rejected, we can apply for reconsideration (s 191). The fee is $357.20.
These are only the government fees for resubmitting at each point. They do not include any ACAT application or any architect's hours needed to amend the plans.
There is no guarantee that the Department will approve the project after any of these steps.