Practical completion in the HIA agreement - can you explain what this actually means?
What the law says
The ACT Government issues the Certificate of Occupancy and Use. It is an offence to occupy or use a building, or part of a building, until a certificate of occupancy has been issued for it (Building Act 2004, A2004-11, s 76). So you cannot live in or rent out the new building until the certificate is issued.
How practical completion works under our HIA agreement
In our HIA agreement, practical completion means that the building works have reached the stage where we, the builder, certify that they have been completed in accordance with the contract, except for minor omissions. Where applicable, it also means we have done all that we are required to do under the contract to enable a certificate of occupancy to be obtained.
We treat practical completion as agreed when we and you sign the Customer Project Walkthrough. The contract also gives us the power to declare that practical completion has been achieved (clause 23.1). That power does not depend on you signing. Minor omissions or defects noted at the walkthrough do not stop practical completion being reached.
Practical completion is not the same as having the Certificate of Occupancy and Use. It comes first, and the certificate follows. Your appointed private building certifier manages the process and lodges the application with Building Registration. This happens after practical completion and takes approximately three weeks, subject to government processes.
CGFB-Q-0185 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?