Questions & Answers › Approvals and planning rules
Is a unit title dual occupancy required to be separately metered?
Yes. A unit title dual occupancy must have separate unit meters. The rules differ for water and electricity, and the utility providers (Icon Water and Evoenergy) have the final say on their networks.
What the rules say
Water. The Utilities (Technical Regulation) (Water and Sewerage Code) Approval 2024 took effect on 1 July 2024. Schedule 2, subsection 5 states:
Mandatory unit metering is to commence for all new multi-unit developments where the Development Application is lodged on or after 1 July 2025.
So if your Development Application is lodged on or after 1 July 2025, each unit must have its own water meter. The units can share one connection to the water network (one "service tie") while the block stays on a single lease, which is the case when the dwellings are unit titled. Separate connections are not mandatory, but they can be done. Icon Water's guidance says sub-metering between the two dwellings is not permitted, so a sub-meter cannot replace a proper unit meter. If the block is instead subdivided into separate leases, each lease must have its own independent connection and Icon Water meter.
Electricity. Under the Unit Titles Act 2001 (A2001-16), each unit needs its own electricity and water meter before unit titles can be approved. Evoenergy sets out its connection requirements in its Service and Installation Rules Manual. Subclause 5.3.5 states:
Separate services for dual occupancy/subdivision will be provided. However, where a separate service is installed to an additional premise, the cost of the second service is to be borne by the customer including any other network modification required. Evoenergy will determine the appropriate point for the connection of the service to each premise.
This metering requirement is set by the utility providers and the unit title rules. It is not part of the Planning (Residential Zones) Technical Specifications 2026 (NI2026-303), although spec 29.1 does require the development to be serviceable and endorsed by the utility providers.
How we handle it
We note the proposed servicing arrangement in the referral to the utility providers. We then check it against the titling you intend (unit title or block subdivision) before confirming what is needed. We apply to Icon Water and Evoenergy on your behalf during the approvals process. Getting your DA approved does not give you utility approval, so we raise servicing early, before the design is finalised.
CGFB-Q-0858 · last reviewed 24 November 2026