In schedule 1, item 9 – what does completion time mean? And when does it start count?
Completion time is the period we have to finish your project, from when construction begins to practical completion. It is counted in working days, not calendar days.
The count starts 15 days after we receive building approval (the stamped plans) from the private certifier.
The time can be extended. If a delay happens, we send you a time delay letter that shows the date it was sent, the number of working days delayed and the reason. Delays in finalising your inclusions choices also extend the completion time.
We back the completion time with a time guarantee. It is set out in your project proposal and in your HIA agreement. Please read the full terms with your HIA agreement.
CGFB-Q-0390 · last reviewed 21 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?