If a natural disaster were to wipe out the build half way through the construction, who’s insurance would be liable for the project? At what stage do we need to seek our own insurance?
If a natural disaster damages or destroys the build part-way through, our construction insurance responds for the building work we are contracted to do. For example, if a storm brings a tree down on a detached addition or Secondary Residence while we are building it, that damage to our work is claimed under our construction insurance. It covers our project only.
Home warranty insurance is different. It protects you if we, as the builder, become insolvent, shut down or for any other reason cannot complete the work. It is not cover for natural disasters.
If your project is an alteration or addition, the existing house is also at risk while it is under construction. Our insurance only covers our construction. It does not extend to all structures on site. As the homeowner, you need to make sure your own home and contents policy covers the existing house while the work is under way. If your insurer will not cover the existing structure, tell us. It may then need to be added to our policy for the length of the build. Our current policy covers existing structures up to $1,500,000 at any one time, and the building work up to $500,000.
When to act: tell your insurance company about the build and check your policies. We will let you know when you need to contact your insurer. Your own cover for the existing structure needs to be in place for the whole time the build is under way, unless we have agreed to add it to our policy.
If you choose to do any work on site yourself, that work is at your own risk. You are liable for fixing any damage you cause.
CGFB-Q-0486 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?