I am entitled to liquidated damages as the project was delayed in reaching practical completion.
What the contract says
Your HIA agreement gives us a set number of working days to finish the project. Only working days are counted, not calendar days. The count starts 15 days after we receive the stamped Building Approval plans from the private certifier. It runs until practical completion, which is when the building work is finished apart from minor omissions.
The completion time can be extended. Only working days count when a delay happens. The completion time is also extended if your inclusions and selections are not finalised in time. If a progress payment is not made when it becomes due, Clause 12 of the contract lets us charge interest and suspend the building works after written notice. The contract also lets us add days to the project schedule to cover a suspension and the rescheduling of trades, suppliers and resources.
Our time guarantee
Once all approvals are in place and construction is ready to start, we work to finish within the timeframe in your signed HIA agreement. If we do not meet it, we will compensate you at $250 per day ($1,750 a week), or provide accommodation in a 5-star hotel, until your project is complete. The guarantee is outlined in your project proposal and reflected in Schedule 1 of your HIA agreement.
The guarantee is subject to reasonable conditions. These include changes you request that affect design, selections or scope, weather and other delays outside our control, restricted or delayed access to the site, and authority, utility or approval delays outside our control.
How we handle it
When a delay happens, we send you a time delay letter. It states the date it was sent, the number of working days delayed and the reason. Those working days are added to the completion time. We also email the letter to you and post a copy to your letterbox.
If you think we have missed the completion time, please email contracts@cgfb.com.au. Tell us the dates you are relying on and attach any documents that support your claim. We will check the working days counted, any time delay letters sent, and the conditions above. Please read the full terms with your HIA agreement.
CGFB-Q-0797 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?