How many minor breaches are allowed before it becomes a DA? Just one or is it unlimited?
What the law says
The Planning (Exempt Development) Regulation 2023 (SL2023-21), schedule 1, section 1.19B, lets you apply for an exemption declaration. It says a development is exempt from development approval despite non-compliance with a requirement. The requirements covered are those in schedule 1, part 1.4 and the Single Dwelling Housing Development Control. The regulation does not set a number of breaches.
Under section 1.19C(2), the Territory Planning Authority can make the declaration only if it is satisfied that:
- the non-compliance is minor;
- building it other than as the rule requires will not adversely affect someone other than the proponent (a change to a neighbour's view does not count as an adverse effect);
- it will not more than minimally increase the environmental impact of the development;
- it will not more than minimally increase shadowing to any habitable room or principal private open space of another block between 9am and 3pm on the winter solstice; and
- if section 1.18 applies, the written information required by section 1.18 has been given to the adjoining occupiers.
The Authority must decide within 10 working days of the application. It can stop the clock by asking for more information. A declaration expires 3 years after it is made.
So the test is whether the non-compliance is minor and meets the points above. It is not a count of breaches.
How we handle it
We use an exemption declaration where a project is otherwise compliant but has one minor breach. Typical breaches are a setback, the building or solar envelope, or the minimum private open space dimensions. We get the declaration first, then Building Approval from a certifier. If there is more than one breach, or the breach is not minor, we lodge a DA.