How long will the project take from start to finish?
For a Secondary Residence, allow roughly 18 months to 2 years from your first design meeting to moving in. There are three main stages: design, approvals and construction. Approvals usually take the longest.
What the law says
A Secondary Residence always needs a Development Approval (DA) before it can get a Building Approval (BA). Under the Planning Act 2023 (A2023-18), the legal timeframe for assessing a DA is 30 working days if no neighbour makes a representation. It is extended by 15 working days if a representation is received. That is only the government's assessment step. Working days leave out weekends and public holidays.
The Building Approval is assessed under the Building Act 2004 (A2004-11). It has no legislated timeframe, so how long it takes varies.
If your block is registered or provisionally registered on the ACT Heritage Register, the development must be endorsed by the ACT Heritage Council (Planning (Residential Zones) Technical Specifications 2026, NI2026-303, specification 23.2). That can add time.
By law, you cannot live in or rent out a new building until a Certificate of Occupancy and Use has been issued.
Extensions are different. An attached or detached extension may skip the DA only if it meets every control in the Single Dwelling Housing Development Controls and the relevant District Controls, as well as the general exemption criteria. These are made under the Planning Act 2023, with the Planning (Exempt Development) Regulation 2023 (SL2023-21). If it does not meet them all, it needs a DA.
How we find it works in practice
Design: usually 14 to 18 weeks. This covers the design meetings, plan revisions and pricing until you approve your final plans and receive your fixed-price proposal.
Planning approvals: generally 8 to 10 months overall. The legal assessment period above is only part of this. The rest is preparing documents, the completeness check, public notification, advice from agencies such as utility providers, any requests for further information, and then the Building Approval.
Construction: most Secondary Residences are completed in around 6 months from when construction starts.
Certificate of Occupancy and Use: after the handover walkthrough, the certifier's application is ideally lodged about a week later. The certificate then takes approximately three weeks, depending on government processing.
Add these stages together, one after another, and you reach the 18 months to 2 years above. Some customers choose to start certain approval applications during design, which can shorten the overall time.
Your build timeframe is set in your contract
Your HIA building agreement states the time we have to finish construction. It is counted in working days, not calendar days, from the start of construction to practical completion. The count starts 15 days after we receive the stamped Building Approval plans from the private certifier. This time can be extended if delays occur. Once all approvals are in place, we work to complete your project within the timeframe in your signed agreement.
Extensions and dual occupancies
We do not publish standard overall timeframes for extensions or dual occupancies. An extension often needs only a Building Approval, so its approvals stage is often shorter. A dual occupancy usually needs a DA that also varies the Crown lease, which can add steps. Please call us on 1300 979 658 and we can talk through what is likely for your project. Your own construction timeframe will be set out in your HIA agreement.