How long will it take to complete the build?
The length of time to complete a project may vary depending on the size, complexity and site conditions.
Compact, detached new homes take an average of 12 to 14 weeks, plus the time required to complete site preparation such as demolition, disconnections, and rerouting of services, site cut and fill and retaining walls.
A similar sixed extension, for example a 1-bedroom master bedroom with an ensuite and living area takes around 14 to 16 weeks plus the time required to complete site preparation such as demolition, disconnections, and rerouting of services, site cut and fill and retaining walls.
Additional time is required for an extension due to trades requiring multiple visits to disconnect services, complete demolition and manage unknown factors that are exposed in the process of connecting the new extension to the existing home.
Our business has a strong history of completing projects from simple, small homes to large custom renovations and extensions.
To ensure that we keep this commitment, we provide a time guarantee for our projects to provide certainty and a safeguard for customers.