Questions & Answers › Approvals and planning rules
How long is a Development Approval (DA) valid for?
What the law says
Under the Planning Act 2023 (A2023-18), a Development Approval (DA) approved after November 2023 generally lasts for 5 years after it takes effect. If your DA was approved earlier, check your Notice of Decision or ask us. Always check your Notice of Decision and the approval conditions, because they apply to your project.
An application can be made to extend the approval. It must be made within 6 months after the end of the 5-year period. To qualify:
- the development must have started and substantially progressed, and
- the development must still be approvable if a DA were lodged at the time of the extension application.
Extensions can be granted more than once, but generally for a combined maximum of 2 additional years.
If construction has not started and substantially progressed, the extension pathway generally is not available. A new DA would generally be needed to proceed.
A single DA can cover development built in stages, if the approval allows for it. Conditions can apply to a particular stage.
How this affects your project with us
Even while a DA is still valid, delays can create problems, such as:
- changes to planning legislation
- updated building code requirements
- expired consultant reports
- new tree or environmental requirements
- changed service authority conditions
- increased construction costs
For this reason, we recommend keeping design, approvals and construction planning moving together.
A valid DA also does not replace Building Approval (BA). You still need a BA before construction can commence.
Reference: Planning Act 2023 (A2023-18) – Development Approval duration and extension provisions; ACT Government – Possible Outcomes – When DA Approval Expires: https://www.planning.act.gov.au/applications-and-assessments/development-applications/after-you-apply/possible-outcomes