How long does it take to get approval for a Secondary Residence in Canberra?
What the law says
A Secondary Residence always needs Development Approval (DA). It cannot go straight to a building certifier. Under the Planning Act 2023 (A2023-18), the legal timeframe for the assessment stage of a DA is 30 working days if no neighbour makes a representation. It is extended by 15 working days if a representation is received. Time spent answering a request for further information does not count towards that period.
Building Approval is not governed by a legislative timeframe, so how long it takes varies.
If your block is registered or provisionally registered on the ACT Heritage Register, the development must comply with any heritage guideline, order or agreement and be endorsed by the ACT Heritage Council (Planning (Residential Zones) Technical Specifications 2026, NI2026-303, specifications 23.1 and 23.2).
If your Crown lease needs varying, that needs approval through a Development Application. A Lease Variation Charge may be payable, depending on what your lease says. The lease is not varied until any charge is paid.
How we find it works in practice
The time for approval can be quite long and varies with the individual block.
The legal timeframe covers only the government's assessment. Around it sit other steps: preparing the application, a completeness check by the planning authority (which can take up to 10 working days), public notification, referrals to bodies such as Icon Water, Evoenergy and Transport Canberra and City Services, and any requests for further information. Building Approval from a private certifier then follows.
The Development Approval component realistically takes 40-50 working days.
Factors which may extend the approval process include:
- Whether the Crown lease of your property needs varying
- Whether your neighbour made any representations about your project
- Whether there are heritage elements to be considered
Overall, planning approvals generally take 8-10 months.