How long does it take to build a Secondary Residence, and when can I move in?
Most Secondary Residences take around 6 months to build, counted from the day construction starts. From your first design meeting to moving in, allow roughly 18 months to 2 years. Approvals usually take the longest.
What the law says
A Secondary Residence always needs Development Approval (DA) before it can get Building Approval. Under the Planning Act 2023 (A2023-18), the legal timeframe for assessing a DA is 30 working days if no neighbour makes a representation. It is extended by 15 working days if a representation is received. Building Approval has no legislated timeframe, so how long it takes varies.
It is against the law to occupy or use a building until a Certificate of Occupancy and Use has been issued for the purpose it will be used for (Building Act 2004, A2004-11, s 69(3) and s 76). You cannot move in or rent out the new building before then.
How we do it
Design: usually 14 to 18 weeks.
Planning approvals: generally 8 to 10 months overall. This includes preparing the application, the completeness check, public notification, advice from agencies and the Building Approval, not just the government's assessment period.
Construction: most Secondary Residences are completed in around 6 months from when construction starts. The exact period is written into your signed HIA agreement as a number of working days, not calendar days. It starts 15 days after we receive the stamped Building Approval plans from your private building certifier. It runs until practical completion.
Our time guarantee: once all approvals are in place and construction is ready to start, we work to finish within the timeframe in your HIA agreement. If we do not meet it, we will compensate you at $250 per day, or provide accommodation in a 5-star hotel, until your project is complete. The guarantee is subject to reasonable conditions. These include changes you request that affect design, selections or scope, weather and other delays outside our control, restricted or delayed access to the site, and authority, utility or approval delays outside our control.
Moving in: practical completion is not the same as moving in. After the handover walkthrough, we gather the installation and compliance certificates. Your private building certifier checks them and issues a Certificate of Completion. The certifier then lodges the application for the Certificate of Occupancy and Use. Ideally this happens about a week after the walkthrough. The certificate then takes about three weeks, depending on government processing. Allow roughly a month after practical completion before you can move in.
What this means for you
Your build timeframe is fixed in your agreement and backed by our time guarantee. Plan for the design and approvals time before construction starts, and for about a month after the walkthrough before you can move in.
CGFB-Q-0845 · last reviewed 24 November 2026