How are residential building disputes dealt with?
What the law says
Part 6A of the Building Act 2004 (A2004-11) sets up a dispute resolution process for residential building disputes.
A residential building dispute is a dispute about a residential building matter. It is between a building owner and either a building practitioner (such as a builder) or a developer (s 127B). A residential building matter includes anything about a residential building work contract, the carrying out of residential building work, or a breach of a statutory warranty (s 127C).
A party to the dispute can lodge it in writing with the Residential Building Dispute Administrator (s 127N). The Construction Occupations Registrar or the Commissioner for Fair Trading can also refer a dispute to the administrator (s 127M).
The administrator can decide not to take a dispute further. Examples are where the lodging party did not take reasonable steps to resolve it before lodging, where it is a security of payment dispute, or where it is about a decision of an authorised insurer or fidelity fund manager (s 127O). The administrator can also refer a dispute to another body that is better placed to deal with it (s 127P).
If the dispute goes ahead, the administrator decides the kind of process and the dispute resolution officer who will run it. The administrator tells each party in writing (s 127Q). Everyone taking part must make a genuine effort to resolve the dispute (s 127D). The administrator can ask a technical building assessor to report on whether work has been carried out, or is defective or incomplete (s 127R). If the dispute is resolved, the officer writes down the agreement. It is confirmed when each party and the administrator sign it (s 127S). What is said and produced in the process is confidential (s 127T). Regulations can prescribe the kinds of process and which disputes cannot go through this process (s 127E).
Separately, the building certifier is appointed by the land owner, not the builder (s 19). The certifier inspects the work at set stages to check it complies with the Act. The certifier must tell the Construction Occupations Registrar about contraventions they become aware of (ss 17A, 50). The certifier's role is about building compliance, not contract disputes.
How we handle it
As soon as you identify an issue or have a concern, raise it with us in writing. Under clause 23 of your building agreement you have 65 working days after completion to notify us of defects. Please add each defect to the warranty log. For contract concerns such as payments, quality of inclusions or communication, email contracts@cgfb.com.au.
If the issue is not resolved and it is about building or planning compliance, talk to your building certifier. You can also make a complaint to Access Canberra.
For contract disputes you can contact:
- Conflict Resolution Service, for formal mediation and dispute resolution
- ACT Civil and Administrative Tribunal
- Access Canberra - Fair Trading
CGFB-Q-0827 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?