Does practical completion mean Certification of Occupancy and Use? Who manages this?
Short answer: No. Practical completion and the Certificate of Occupancy and Use are two different things. Practical completion comes first. The certificate follows it.
What the law says
The ACT Government issues the Certificate of Occupancy and Use. You cannot legally live in or rent out the new building until it has been issued.
How we do it
Practical completion means the building works have reached the stage where we, the builder, certify they have been completed in accordance with the contract, except for minor omissions. It also means we have done all that the contract requires of us so that a certificate of occupancy can be obtained. It is formally reached when you and we sign the Customer Project Walkthrough.
After the walkthrough, we gather the installation and compliance certificates. Your private building certifier checks them and issues a Certificate of Completion. Your certifier then lodges the application for the Certificate of Occupancy and Use with Building Registration. Only your certifier can lodge it.
The certificate takes approximately three weeks after that, subject to government processes. Your private building certifier manages the process.
The certifier is appointed by you, the owner, not by us. We often work with certifiers we know, because communication is easier. You can nominate your own private certifier if you prefer.
CGFB-Q-0434 · last reviewed 24 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?